Client: Kapitol Group
Value: $300,000
Date: 2020
Location: Inner Suburban Melbourne
Scope of Works
+ Demolition of 3 storey brick wall by hand and without scaffold protection (due to dispute between developer and neighbour).
+ Traffic management – tight footprint for load out.
+ Noise, dust and vibration controls.
+ Mobile cranage – lifting plant and equipment.
+ Asbestos removal. Recycling & Waste Management.
+ Temporary works engineering and design: propping installation. + Underpins removal (up to 2m deep).
Key Challenges & Outputs
+ On time, on budget. Nil incidents.
+ Key stakeholder engagement. Existing neighbour dispute.
+ Mini/medium excavators – 3t to 20t – bobcats. Mobile Crane. + 1,100t C&D Waste Recycled | 85% Diversion (Recovery) Rate.